|
Three Mile Island
(TMI-2)
At 4:00 AM on March 28, 1979, a reactor at the Three Mile Island
unit two (TMI-2) nuclear power facility near Harrisburg,
Pennsylvania suddenly overheated, releasing radioactive gases.
During the ensuing tension-packed week, scientists scrambled to
prevent the nightmare of a meltdown, officials rushed in to calm
public fears, and thousands of residents fled to emergency shelters.
Equipment failure, human error, and bad luck would work together to
create America's worst nuclear accident.
-
The reactor's fuel core became uncovered and more than one third
of the fuel melted.
-
Inadequate instrumentation and training programs at the time
hampered operators' ability to respond to the accident.
-
The accident was accompanied by communications problems that led
to conflicting information available to the public, contributing
to the public's fears
-
Radiation was released from the plant. The releases were not
serious and were not health hazards. This was confirmed by
thousands of environmental and other samples and measurements
taken during the accident.
-
The containment building worked as designed. Despite melting of
about one-third of the fuel core, the reactor vessel itself
maintained its integrity and contained the damaged fuel.
By 8:00 a.m., after cooling water was
lost and temperatures soared
above 5,000 degrees, the top portion of the reactor's 150-ton
core collapsed and melted.
It was never supposed to happen. In
the predawn hours of March 28, 1979, a pressure valve suddenly
malfunctioned at the Three Mile Island nuclear power plant near
Harrisburg, Pennsylvania. What occurred next--a combination of
technical failure, human error, and bad luck--would result in the
worst nuclear accident in American history. For five nerve-wracking
days, engineers struggled to control a runaway reactor, government
officials debated whether to evacuate the area, and residents
contemplated the ultimate horror of a nuclear meltdown.
The accident began about 4:00 a.m. on March 28, 1979, when the plant
experienced a failure in the secondary, non-nuclear section of the
plant. The main feedwater pumps
stopped running, caused by either a mechanical or electrical
failure, which prevented the steam
generators from removing
heat. First the turbine, then the reactor, automatically shut
down. Immediately, the pressure in the primary system (the nuclear
portion of the plant) began to increase. In order to prevent that
pressure from becoming excessive, the pilot-operated relief valve (a
valve located at the top of the pressurizer) opened. The valve
should have closed when the pressure decreased by a certain amount,
but it did not. Signals available to the operator failed to show
that the valve was still open. As a result, cooling water poured out
of the stuck-open valve and caused the core of the reactor to
overheat.
As coolant flowed from the core through the pressurizer, the
instruments available to reactor operators provided confusing
information. There was no instrument that showed the level of
coolant in the core. Instead, the operators judged the level of
water in the core by the level in the pressurizer, and since it was
high, they assumed that the core was properly covered with coolant.
In addition, there was no clear signal that the pilot-operated
relief valve was open. As a result, as alarms rang and warning
lights flashed, the operators did not realize that the plant was
experiencing a loss-of-coolant accident. They took a series of
actions that made conditions worse by simply reducing the flow of
coolant through the core.
Because adequate cooling was not available, the nuclear fuel
overheated to the point at which the zirconium cladding (the long
metal tubes which hold the nuclear fuel pellets) ruptured and the
fuel pellets began to melt.
It was later found that about one-half of
the core melted during the
early stages of the accident. Although the TMI-2 plant
suffered a severe core meltdown, the most dangerous kind of nuclear
power accident, it did not produce the worst-case consequences that
reactor experts had long feared. In a worst-case accident, the
melting of nuclear fuel would lead to a breach of the walls of the
containment building and release massive quantities of radiation to
the environment. But this did not occur in the Three Mile Island
incident.
Three Mile Island Unit 2 was too badly damaged and contaminated to
resume operations.
Early in the cleanup, Unit 2 was completely severed from any
connection to TMI Unit 1. Defueling the TMI-2 reactor vessel was the
heart of the cleanup. The damaged fuel remained underwater
throughout the defueling. In October, 1985, after nearly six years
of preparations, workers standing on a platform atop the reactor and
manipulating long-handled tools began lifting the fuel into
canisters that hung beneath the platform. In all, 342 fuel canisters
were shipped safely for long-term storage at the Idaho National
Laboratory, a program that was completed in April, 1990.
Today, the TMI-2 reactor is permanently shut down and defueled, with
the reactor coolant system drained, the radioactive water
decontaminated and evaporated, radioactive waste shipped off-site to
an appropriate disposal site, reactor fuel and core debris shipped
off-site to a Department of Energy facility, and the remainder of
the site being monitored. The owner says it will keep the facility
in long-term, monitored storage until the operating license for the
TMI-1 plant expires at which time both plants will be
decommissioned. TMI-1's license expires in 2034.
Chernobyl
Return to
Top^

At 1:23 AM on April 26, 1986, two explosions ripped through the
Unit 4 reactor of the Chernobyl Nuclear Power Plant in Chernobyl,
Ukraine, of the former USSR. The reactor block and adjacent
structure were wrecked by the initial explosion. Nearby buildings
were ignited by burning graphite projectiles. Radioactive particles
swept across the Ukraine, Belarus, the western portion of Russia and
eventually spread across Europe and the whole Northern Hemisphere.
The accident followed a safety experiment in which the plant was
operated outside of its designed parameters at very low power and
unfavorable cooling conditions.
The radioactivity released was estimated to be about
two hundred times
that of the combined releases in the bombing of Hiroshima and
Nagasaki. Millions of people were exposed to the radiation in
varying doses.

|
Prior to a routine shut-down, the reactor crew at Chernobyl-4
began preparing for a test to determine how long
turbines would spin and supply power following a loss of
main electrical power supply. Similar tests had already
been carried out at Chernobyl and other plants, despite
the fact that these reactors were known to be very
unstable at low power settings.
A series of operator actions, including the disabling of
automatic shutdown mechanisms, preceded the attempted
test early on that fateful day. As flow of coolant
water diminished, power output increased. When the
operator moved to shut down the reactor from its
unstable condition arising from previous errors,
a peculiarity of
the design caused a dramatic power surge.
On April 26th, 1986, at 1:23 am, Alexander Akimov did
what he and thousands of other nuclear plant operators
have been trained to do. When confronted with
confusing reactor indications, he initiated an emergency
shutdown of Unit 4 of the large electricity generating
station near Pripyat in the Ukraine.
By doing so, he unwittingly initiated an explosion whose
effects continue to be felt throughout the world.
Before pressing the AZ button - used to initiate an
emergency shutdown - Akimov and his fellow operators
were immersed in the conduct of a special test.
The procedure was designed to prove that the reactor
would be provided with sufficient cooling water even if
a complete loss of power to the large electric
generating complex occurred while the emergency cooling
system was inoperable.
According to engineering calculations, the inertia of
the plant's big 500 MW electric turbines would allow
them to generate enough electricity to keep cooling
water pumps operating during the 30 to 50 second delay
required to start the emergency diesel generators.
The test was planned for a time when the plant was to be
shut down for routine maintenance and its power output
was not needed for the national electrical grid.
|
01:23:04
The actual test procedure begins with the
turbine feed valves being closed to start
the turbine coasting.
01:23:10
The automatic control rods were now
withdrawn from the core. This was a normal
occurrence and was designed to compensate
for the drop in reactivity after the turbine
feed valves were closed. The average
withdrawal time was 10 seconds. This
decrease is usually precipitated by a
decrease in the quantity of steam in the
core caused by an increase in cooling system
pressure. This time the amount of steam did
not decrease as there was a reduced feed
water flow rate to the core.
01:23:21
The quantity of steam in the core was at a
point that due to the positive void
coefficient -
a measurement of how the
reactor responds to increased
steam
formation in the water coolant -
a further increase in steam would create a
rapid increase in power.
01:23:35
There was now an uncontrolled increase in
the quantity of steam in the core.
01:23:40
The operator now pressed the emergency
button (AZ-5). The control rods now started
to enter the core from the top. This had the
effect of concentrating the reactivity in
the bottom of the core.
01:23:44
The reactor power had now peaked at
approximately 100 times the reactors rated
value.
01:23:45
Fuel pellets had now started to shatter and
as they then reacted with the coolant, this
produced a burst of high pressure in the
fuel channels.
01:23:49
The fuel channels ruptured.
01:24:00
At this time there was thought to be two
explosions, one a steam explosion and the
other being a product of the fuel vapor
expansion. These explosions lifted the pile
cap of the reactor vessel which allowed air
to enter. This resulted in the ignition of
flammable gas and a reactor fire ensued. |
The fuel elements ruptured and the resultant explosive force of
steam lifted off the cover plate of the reactor,
releasing fission products to the atmosphere. A second
explosion threw out fragments of burning fuel and
graphite from the core and allowed air to rush in,
causing the graphite moderator to burst into flames.
There is some dispute among experts about the character
of this second explosion.
Over 1200 tons of graphite burned for nine days,
despite dumping over 5000 tons of boron, dolomite, sand, clay and lead onto the
burning core by helicopter in an effort to extinguish
the blaze, causing the main release of radioactivity
into the environment. The
fire eventually extinguished itself when the core melted
and flowed into the lower part of the building, then
solidified, sealing off the entry. About 71% of
the radioactive fuel in the core (about 135 metric tons)
remained uncovered for about 10 days until cooling and
solidification took place.

Within seven months of the accident the reactor was
contained within the purpose built 'sarcophagus' which
is approximately 180 feet high by 180 feet long and is
supported on the remains of the old reactor building.
Although this building was supposed to last for 30
years, it is already showing serious signs of
deterioration because of poor standards maintained
during construction. Another problem is the fact that
the concrete is suffering from constant irradiation and
a considerable temperature differential between the
inner and outer faces.
The accident destroyed the Chernobyl-4 reactor and
killed 30 people, including 28 from radiation exposure.
A further 209 on site and involved with the clean-up
were treated for acute radiation poisoning and among
these, 134 cases were confirmed (all of whom apparently
recovered). Nevertheless 19 of these subsequently died
from effects attributable to the accident. Nobody
off-site suffered from acute radiation effects. However,
large areas of Belarus, Ukraine, Russia and beyond were
contaminated in varying degrees.
Following the accident, questions arose on the future of
the plant and its eventual fate. All work on the
unfinished reactors 5 and 6 was halted three years
later. However, the trouble at the Chernobyl plant did
not end with the disaster in reactor 4. The damaged
reactor was sealed off with concrete. The Ukrainian
government continued to let the three remaining reactors
operate because of an energy shortage in the country. A
fire broke out in the turbine building of reactor 2 in
1991; the authorities subsequently declared the reactor
damaged beyond repair and had it taken offline. Reactor
1 was decommissioned in November 1996 as part of a deal
between the Ukrainian government and international
organizations such as the IAEA to end operations at the
plant. On December 15, 2000, then-President Leonid
Kuchma personally turned off Reactor 3 in an official
ceremony, effectively shutting down the entire plant
transforming the Chernobyl plant from energy producer to
energy consumer. |
|